Project Description
Replacement of the existing bridge structure with a 14’ x 8’ precast concrete box culvert on SR 119 over Zellers Run. Reconstruction of the approach roadway, temporary bypass pumping of stream, associated traffic control, and other miscellaneous construction.
- Three Phase Project on SR 119 with 6 Lanes of Traffic Including two turning lanes on North and South Ends of Project Limits
- Installed 13 Precast Concrete Box Culvert sections totaling 87 LF
- Cast-in-Place Outlet Floor and Wing Sections 9’ x 14’ around existing utilities
- 1291 CY Class I Excavation
- 1008 CY Class III Excavation
- 7557 SY Bituminous Asphalt Paving
- 798 LF Concrete Curb
- 5511 LB Reinforcement Bars
- 918 CY Selected Borrow Aggregate
- 1010 LF Trenching and Backfill
- Temporary Excavation Support and Protection System
- Temporary Bypass Pumping of Sanitary Sewer
- Sanitary Sewer Relocation
- 239 LF Ductile Iron Sewer Pipe with 53LF of Concrete Encasement
- Installation of 12’ x 8’ x 12’ Precast Concrete Sewer Vault, under SR 30 Overpass, with a Base, Riser, and Lid Total Weight of 79,133 LBS