Project Description
Install Reinforced Concrete Jacking Pit for a One Track In-Floor Jacking System with construction of insulated enclosure for hydraulic power unit.
- Excavate and install sheet pile shoring system
- Drive fourteen HP 12 x 53 Steel Bearing Piles
- Install anchor rod eyes, sump pit and suction piping, compressed air piping, steel cover plates and access hatch, and ladder
- Furnish and install two 10,000 lb. capacity jib cranes with chain hoists
- Furnish and install all electrical service devices including electrical conduits, wiring, distribution panels, breakers, disconnect switches, transformer, receptacles, junction boxes, lights, and connection to existing power source
- Furnish and install 9’ x 14’ Insulated Enclosure for Hydraulic power Unit
- Relocate Existing Sheds
- Furnish and install Canopy Siding