Project Description
Earthwork and site development for 1,050 MW, 2×1 combined-cycle power plant constructed on a brownfied redevelopment property. Excavation and grading for temporary facilities and roadway. Excavation and grading for power block and roadway. Drainage work for entire site. Install soil/nail retaining wall and maintain Erosion Sediment Controls.
- 12,195 CY Strip/Haul and stockpile topsoil
- 53,623 SY Erosion Control Blankets
- 293,945 CY Mass Grading Excavation
- 33,722 CY Mass Grading Blasting
- 72,103 SY of surface stone for Laydown Area, Craft Parking, Loop Road, and Office Complex Area
- 17,434 SF Soil Nail Retaining Wall
- 16,000 CY Imported Select Fill
- 1,000 LF 12”-36” RCP Pipe
- 14,200 LF 15”-30” HDPE Pipe
- 326 Tons of Stone Aprons
- Installation of 13 Drainage Manholes
- 5,900 SY of Asphalt Paving